HARMOND AVENUE AREA WATER AND WASTEWATER SYSTEM RENEWAL

SANTA CLARA CONSTRUCTION LTD
Needs a closer lookComplete — fully paid
Construction

This is a construction contract with SANTA CLARA CONSTRUCTION LTD to deliver “HARMOND AVENUE AREA WATER AND WASTEWATER SYSTEM RENEWAL”. The city authorized spending up to $3,153,642, and $3,469,050 has been paid so far (110% of the ceiling).

Authorized (spending ceiling)
$3,153,642
Ordered / committed
$3,153,642 (100%)
Actually paid
$3,469,050 (110%)
from 28 checks in the city checkbook
Contract record lists $2,877,386 in its delivery-order field — understates actual checks.
Timeline
Aug 18, 2020
Kicked off May 12, 2021 · last check Nov 3, 2025

Why this status?

  • Payments ($3,469,050) exceed the authorized ceiling ($3,153,642) — worth a closer look.
  • No expiration date on record — timeline signals can't be computed.

These are transparent signals, not judgments. A large unspent balance may be a legitimate multi-year ceiling or indefinite-delivery contract.

Payments on this contract

28 checkbook lines totaling $3,469,050 are booked directly against this contract — this is the amount actually paid.
The contract’s own record lists $2,877,386 in its “delivery-order referenced” field — a $591,664 understatement. That field only counts payments made through delivery orders, so we treat the checkbook total above as the real amount paid.
Where the money came fromEnterprise (fee-supported) · 100%
Enterprise (fee-supported) · Water Improvements--Nva, Wastewater Improvements--Nva$3,469,050 (100%)

Funding source is read from the fund each check was drawn on. It tells you who is accountable: voters & Council for bond/general-capital money, ratepayers & utility commissions for enterprise money, Council for the General Fund.

What the money paid for
CONSTRUCTION SERVICES, HEAVY$3,469,050 (100%)

Grouped from the city’s own line-item descriptions. Vague or generic labels are themselves a transparency signal worth questioning.

See all 28 individual checks
DateAmountProject / fundWhat forStatus
Nov 3, 2025$42,137Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Nov 3, 2025$437,278Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Jan 18, 2024$26,457Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Jan 18, 2024$85,792Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Oct 2, 2023$200,618Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Oct 2, 2023$216,044Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Sep 6, 2023$29,016Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Sep 6, 2023$2,745Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Aug 24, 2022$133,318Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Aug 24, 2022$2,280Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Apr 12, 2022$93,738Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Apr 12, 2022$21,530Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Feb 16, 2022$110,581Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Dec 29, 2021$188,456Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Dec 29, 2021$123,106Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Nov 17, 2021$130,324Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Oct 20, 2021$104,589Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Oct 20, 2021$1,033Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Sep 22, 2021$153,070Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Sep 22, 2021$137,669Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Aug 18, 2021$271,764Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Aug 18, 2021$998Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Jul 22, 2021$160,227Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Jul 22, 2021$158,066Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Jun 23, 2021$136,266Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
Jun 23, 2021$298,387Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
May 12, 2021$93,430Harmon Avenue Area Wastewater RenewalWastewater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid
May 12, 2021$110,133Harmon Avenue Area Water RenewalWater Improvements--NvaCONSTRUCTION SERVICES, HEAVYPaid

Linked via the contract number appearing as a payment’s source document (rf_doc_id = 20081701011) in the Austin checkbook. See all payments to this vendor →

Accountability

Administered by
Contract and Land Management Department
Delivered by (1 firm)
SANTA CLARA CONSTRUCTION LTD

We couldn’t automatically match this contract to a City Council vote (the voting-record dataset starts in 2023, and older or consent-agenda items may not match by name). Most contracts are approved collectively on the Council consent agenda — so accountability runs through the managing department above and the Council vote on the award date, not an individual sponsor.

Documents & oversight

Contract type
Direct contract — billed against this contract number.

Assessing delivery vs. commitment: Austin doesn’t publish structured project milestones, so we can’t auto-verify that the work matches the contract. What we can do is show what the money was invoiced for (above) and link the approved scope — then, where it matters, dispatch a Spotter to confirm the work on the ground. Contracts whose purpose is well-documented vs. vague is exactly the signal that tells us where to look first.

Source & provenance

Contract number 20081701011 (CT) · Department 6100 · Managed by Contract and Land Management Department · Competitive Acquisition
From snapshot 2026-07-28.