HORNSBY BEND TRANSFER PUMP STATION AND IRRIGATION SYSTEM IMP

PGC GENERAL CONTRACTORS, LLC
also known as PEABODY GENERAL CONTRACTORS
MonitorComplete — fully paid
Construction

This is a construction contract with PGC GENERAL CONTRACTORS, LLC to deliver “Hornsby Bend Transfer Pump Station and Irrigation System Imp”. The city authorized spending up to $16,407,847, and $16,226,149 has been paid so far (99% of the ceiling).

Authorized (spending ceiling)
$16,407,847
Ordered / committed
$16,407,847 (100%)
Actually paid
$16,226,149 (99%)
from 34 checks in the city checkbook
Contract record lists $15,179,304 in its delivery-order field — understates actual checks.
Timeline
Dec 17, 2020
Kicked off May 25, 2021 · last check Oct 31, 2025

Why this status?

  • High-dollar contract ($16,407,847) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.

These are transparent signals, not judgments. A large unspent balance may be a legitimate multi-year ceiling or indefinite-delivery contract.

Payments on this contract

34 checkbook lines totaling $16,226,149 are booked directly against this contract — this is the amount actually paid.
The contract’s own record lists $15,179,304 in its “delivery-order referenced” field — a $1,046,845 understatement. That field only counts payments made through delivery orders, so we treat the checkbook total above as the real amount paid.
Where the money came fromEnterprise (fee-supported) · 100%
Enterprise (fee-supported) · Wastewater Improvements--Nva$16,226,149 (100%)

Funding source is read from the fund each check was drawn on. It tells you who is accountable: voters & Council for bond/general-capital money, ratepayers & utility commissions for enterprise money, Council for the General Fund.

What the money paid for
CONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANT$16,226,149 (100%)

Grouped from the city’s own line-item descriptions. Vague or generic labels are themselves a transparency signal worth questioning.

See all 34 individual checks
DateAmountProject / fundWhat forStatus
Oct 31, 2025$75,393Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Jul 9, 2025$218,121Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Nov 1, 2024$200,000Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
May 9, 2024$400,000Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Feb 22, 2024$73,386Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Dec 20, 2023$79,945Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Aug 25, 2023$10,095Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Aug 7, 2023$111,451Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Jul 10, 2023$219,088Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
May 31, 2023$668,472Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Apr 28, 2023$255,325Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Mar 28, 2023$244,903Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Mar 22, 2023$94,716Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Jan 30, 2023$70,157Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Dec 16, 2022$258,024Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Nov 18, 2022$353,010Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Oct 20, 2022$563,002Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Oct 13, 2022$472,114Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Aug 18, 2022$372,262Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Jul 28, 2022$224,900Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Jun 28, 2022$604,550Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Jun 1, 2022$635,270Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
May 2, 2022$548,052Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Apr 14, 2022$200,221Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Feb 24, 2022$731,671Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Jan 31, 2022$653,723Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Dec 28, 2021$940,032Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Nov 22, 2021$1,122,093Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Oct 27, 2021$610,591Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Oct 8, 2021$1,001,355Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Aug 18, 2021$1,318,558Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Jul 29, 2021$1,543,373Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
Jun 23, 2021$420,574Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid
May 25, 2021$931,721Hornsby Bend Irrigation System ImprovementsWastewater Improvements--NvaCONSTRUCTION AND UPGRADES, WASTEWATER TREATMENT PLANTPaid

Linked via the contract number appearing as a payment’s source document (rf_doc_id = 20121600156) in the Austin checkbook. See all payments to this vendor →

Accountability

Administered by
Contract and Land Management Department
Delivered by (1 firm)
PGC GENERAL CONTRACTORS, LLC

We couldn’t automatically match this contract to a City Council vote (the voting-record dataset starts in 2023, and older or consent-agenda items may not match by name). Most contracts are approved collectively on the Council consent agenda — so accountability runs through the managing department above and the Council vote on the award date, not an individual sponsor.

Documents & oversight

Project (city records)
Hornsby Bend Transfer Pump Station and Irrigation System Imp
Contract type
Direct contract — billed against this contract number.

Assessing delivery vs. commitment: Austin doesn’t publish structured project milestones, so we can’t auto-verify that the work matches the contract. What we can do is show what the money was invoiced for (above) and link the approved scope — then, where it matters, dispatch a Spotter to confirm the work on the ground. Contracts whose purpose is well-documented vs. vague is exactly the signal that tells us where to look first.

Source & provenance

Contract number 20121600156 (CT) · Department 6100 · Managed by Contract and Land Management Department · Competitive Acquisition
From snapshot 2026-07-28.