SPRINGDALE AND 290 WATER LINE IMPROVEMENTS

AUSTIN UNDERGROUND INC
NominalComplete — fully paid
Construction

This is a construction contract with AUSTIN UNDERGROUND INC to deliver “SPRINGDALE AND 290 WATER LINE IMPROVEMENTS”. The city authorized spending up to $7,064,341, and $6,855,136 has been paid so far (97% of the ceiling).

Authorized (spending ceiling)
$7,064,341
Ordered / committed
$7,064,341 (100%)
Actually paid
$6,855,136 (97%)
from 23 checks in the city checkbook
Contract record lists $6,279,865 in its delivery-order field — understates actual checks.
Timeline
Jun 24, 2022
Kicked off Feb 1, 2022 · last check Sep 16, 2025

Why this status?

  • No expiration date on record — timeline signals can't be computed.

These are transparent signals, not judgments. A large unspent balance may be a legitimate multi-year ceiling or indefinite-delivery contract.

Payments on this contract

23 checkbook lines totaling $6,855,136 are booked directly against this contract — this is the amount actually paid.
The contract’s own record lists $6,279,865 in its “delivery-order referenced” field — a $575,270 understatement. That field only counts payments made through delivery orders, so we treat the checkbook total above as the real amount paid.
Where the money came fromEnterprise (fee-supported) · 100%
Enterprise (fee-supported) · Water Improvements--Nva$6,855,136 (100%)

Funding source is read from the fund each check was drawn on. It tells you who is accountable: voters & Council for bond/general-capital money, ratepayers & utility commissions for enterprise money, Council for the General Fund.

What the money paid for
Drilling and Boring Services, Horizontal Directional (HDD an$6,855,136 (100%)

Grouped from the city’s own line-item descriptions. Vague or generic labels are themselves a transparency signal worth questioning.

See all 23 individual checks
DateAmountProject / fundWhat forStatus
Sep 16, 2025$21,155Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Jun 4, 2025$342,757Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Mar 20, 2024$24,605Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Dec 20, 2023$186,753Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Oct 20, 2023$152,593Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Sep 20, 2023$66,888Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Aug 18, 2023$439,263Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Jul 20, 2023$46,636Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Jun 26, 2023$264,782Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
May 12, 2023$225,418Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
May 2, 2023$399,948Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Mar 22, 2023$291,660Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Feb 24, 2023$181,286Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Jan 23, 2023$197,094Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Dec 21, 2022$902,629Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Nov 14, 2022$225,735Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Oct 13, 2022$113,162Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Aug 12, 2022$116,996Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Jul 26, 2022$238,948Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Jul 1, 2022$981,446Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
May 16, 2022$852,779Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Mar 30, 2022$497,317Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid
Feb 1, 2022$85,287Transmission / Distribution 3960 ParentWater Improvements--NvaDrilling and Boring Services, Horizontal Directional (HDD anPaid

Linked via the contract number appearing as a payment’s source document (rf_doc_id = 21092401032) in the Austin checkbook. See all payments to this vendor →

Accountability

Administered by
Contract and Land Management Department
Delivered by (1 firm)
AUSTIN UNDERGROUND INC

We couldn’t automatically match this contract to a City Council vote (the voting-record dataset starts in 2023, and older or consent-agenda items may not match by name). Most contracts are approved collectively on the Council consent agenda — so accountability runs through the managing department above and the Council vote on the award date, not an individual sponsor.

Documents & oversight

Contract type
Direct contract — billed against this contract number.

Assessing delivery vs. commitment: Austin doesn’t publish structured project milestones, so we can’t auto-verify that the work matches the contract. What we can do is show what the money was invoiced for (above) and link the approved scope — then, where it matters, dispatch a Spotter to confirm the work on the ground. Contracts whose purpose is well-documented vs. vague is exactly the signal that tells us where to look first.