This is a construction contract with DENUCCI CONSTRUCTORS L L C to deliver “AIRPORT BOULEVARD - N. LAMAR BLVD TO 55TH STREET”. The city authorized spending up to $13,973,985, and $13,827,217 has been paid so far (99% of the ceiling).

Authorized (spending ceiling)
$13,973,985
Ordered / committed
$13,973,985 (100%)
Actually paid
$13,827,217 (99%)
from 29 checks in the city checkbook
Contract record lists $7,587,169 in its delivery-order field — understates actual checks.
Timeline
Aug 19, 2022
Kicked off Sep 12, 2022 · last check Apr 3, 2025

Why this status?

  • High-dollar contract ($13,973,985) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.

These are transparent signals, not judgments. A large unspent balance may be a legitimate multi-year ceiling or indefinite-delivery contract.

Payments on this contract

29 checkbook lines totaling $13,827,217 are booked directly against this contract — this is the amount actually paid.
The contract’s own record lists $7,587,169 in its “delivery-order referenced” field — a $6,240,049 understatement. That field only counts payments made through delivery orders, so we treat the checkbook total above as the real amount paid.
Where the money came fromGeneral Capital (bonds) · 100%
General Capital (bonds) · GCP-Mobility P1/2016, ATD Transportation CIP$13,827,217 (100%)

Funding source is read from the fund each check was drawn on. It tells you who is accountable: voters & Council for bond/general-capital money, ratepayers & utility commissions for enterprise money, Council for the General Fund.

What the money paid for
Concrete$13,827,217 (100%)

Grouped from the city’s own line-item descriptions. Vague or generic labels are themselves a transparency signal worth questioning.

See all 29 individual checks
DateAmountProject / fundWhat forStatus
Apr 3, 2025$588,203Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Apr 3, 2025$48,700Traffic Impact Analysis (TIA) Mitigation Fee In-LieuATD Transportation CIPConcretePaid
Sep 18, 2024$130,254Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Aug 2, 2024$221,235Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Jun 12, 2024$341,939Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
May 8, 2024$2,457,819Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Apr 29, 2024$869,910Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Mar 6, 2024$248,853Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Feb 9, 2024$262,286Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Jan 12, 2024$178,718Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Dec 27, 2023$242,570Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Dec 6, 2023$52,250Traffic Impact Analysis (TIA) Mitigation Fee In-LieuATD Transportation CIPConcretePaid
Dec 6, 2023$597,310Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Nov 7, 2023$382,358Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Oct 5, 2023$671,373Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Sep 11, 2023$430,831Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Aug 10, 2023$294,149Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Jul 7, 2023$488,053Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Jul 5, 2023$178,372Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Jun 8, 2023$560,035Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
May 8, 2023$663,874Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Apr 6, 2023$445,856Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Mar 8, 2023$228,144Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Feb 9, 2023$594,878Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Jan 10, 2023$405,482Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Dec 9, 2022$1,057,817Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Nov 8, 2022$349,440Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Oct 18, 2022$409,352Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid
Sep 12, 2022$427,155Corridor Program - 2016 BondGCP-Mobility P1/2016ConcretePaid

Linked via the contract number appearing as a payment’s source document (rf_doc_id = 22051700575) in the Austin checkbook. See all payments to this vendor →

Accountability

Administered by
Contract and Land Management Department
Delivered by (1 firm)
DENUCCI CONSTRUCTORS L L C

We couldn’t automatically match this contract to a City Council vote (the voting-record dataset starts in 2023, and older or consent-agenda items may not match by name). Most contracts are approved collectively on the Council consent agenda — so accountability runs through the managing department above and the Council vote on the award date, not an individual sponsor.

Documents & oversight

Contract type
Direct contract — billed against this contract number.

Assessing delivery vs. commitment: Austin doesn’t publish structured project milestones, so we can’t auto-verify that the work matches the contract. What we can do is show what the money was invoiced for (above) and link the approved scope — then, where it matters, dispatch a Spotter to confirm the work on the ground. Contracts whose purpose is well-documented vs. vague is exactly the signal that tells us where to look first.

Source & provenance

Contract number 22051700575 (CT) · Department 6100 · Managed by Contract and Land Management Department · Competitive Acquisition
From snapshot 2026-07-28.