Back to all contracts

WALNUT CREEK WWTP GAS SCRUBBER SYSTEMS RENEWAL

MATOUS CONSTRUCTION II, LTD
also known as MATOUS CONSTRUCTION, LTD OR MATOUS CONSTRUCTION
Needs a closer lookComplete — fully paid
Construction

This is a construction contract with MATOUS CONSTRUCTION II, LTD to deliver “WALNUT CREEK WWTP GAS SCRUBBER SYSTEMS RENEWAL”. The city authorized spending up to $6,565,953, and $7,011,929 has been paid so far (107% of the ceiling).

Authorized (spending ceiling)
$6,565,953
Ordered / committed
$6,565,953 (100%)
Actually paid
$7,011,929 (107%)
from 21 checks in the city checkbook
Contract record lists $3,169,172 in its delivery-order field — understates actual checks.
Timeline
Aug 21, 2023
Kicked off Mar 22, 2023 · last check Jun 2, 2025

Why this status?

  • Payments ($7,011,929) exceed the authorized ceiling ($6,565,953) — worth a closer look.
  • No expiration date on record — timeline signals can't be computed.

These are transparent signals, not judgments. A large unspent balance may be a legitimate multi-year ceiling or indefinite-delivery contract.

Payments on this contract

21 checkbook lines totaling $7,011,929 are booked directly against this contract — this is the amount actually paid.
The contract’s own record lists $3,169,172 in its “delivery-order referenced” field — a $3,842,757 understatement. That field only counts payments made through delivery orders, so we treat the checkbook total above as the real amount paid.
Where the money came fromEnterprise (fee-supported) · 100%
Enterprise (fee-supported) · Wastewater Improvements--Nva$7,011,929 (100%)

Funding source is read from the fund each check was drawn on. It tells you who is accountable: voters & Council for bond/general-capital money, ratepayers & utility commissions for enterprise money, Council for the General Fund.

What the money paid for
Electrical$7,011,929 (100%)

Grouped from the city’s own line-item descriptions. Vague or generic labels are themselves a transparency signal worth questioning.

See all 21 individual checks
DateAmountProject / fundWhat forStatus
Jun 2, 2025$175,298Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Feb 14, 2025$187,648Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Nov 20, 2024$19,764Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Oct 23, 2024$125,028Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Aug 23, 2024$132,091Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Jun 20, 2024$70,514Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
May 22, 2024$826,847Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Apr 17, 2024$389,557Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Mar 19, 2024$525,329Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Feb 23, 2024$532,003Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Jan 12, 2024$819,218Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Dec 22, 2023$39,459Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Nov 27, 2023$547,184Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Nov 1, 2023$689,048Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Sep 20, 2023$312,950Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Sep 7, 2023$403,110Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Jul 20, 2023$575,719Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Jun 29, 2023$109,817Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
May 18, 2023$145,968Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Apr 19, 2023$320,376Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid
Mar 22, 2023$65,001Walnut Creek WWTP Scrubber RehabilitationWastewater Improvements--NvaElectricalPaid

Linked via the contract number appearing as a payment’s source document (rf_doc_id = 22121400131) in the Austin checkbook. See all payments to this vendor →

Accountability

Administered by
Contract and Land Management Department
Delivered by (1 firm)
MATOUS CONSTRUCTION II, LTD

We couldn’t automatically match this contract to a City Council vote (the voting-record dataset starts in 2023, and older or consent-agenda items may not match by name). Most contracts are approved collectively on the Council consent agenda — so accountability runs through the managing department above and the Council vote on the award date, not an individual sponsor.

Documents & oversight

Contract type
Direct contract — billed against this contract number.

Assessing delivery vs. commitment: Austin doesn’t publish structured project milestones, so we can’t auto-verify that the work matches the contract. What we can do is show what the money was invoiced for (above) and link the approved scope — then, where it matters, dispatch a Spotter to confirm the work on the ground. Contracts whose purpose is well-documented vs. vague is exactly the signal that tells us where to look first.

Source & provenance

Contract number 22121400131 (CT) · Department 6100 · Managed by Contract and Land Management Department · Competitive Acquisition
From snapshot 2026-07-28.