AUSTIN HISTORY CENTER/FAULK LIBRARY CMR

SPAWGLASS CONTRACTORS INC
Needs a closer lookTerm ended
Other Contracting

This is a other contracting master agreement (a spending ceiling drawn down over time via delivery orders) with SPAWGLASS CONTRACTORS INC to deliver “AUSTIN HISTORY CENTER/FAULK LIBRARY CMR”. The city authorized spending up to $14,271,973, and $7,983,510 has been paid so far (56% of the ceiling).

Authorized (spending ceiling)
$14,271,973
Ordered / committed
$14,271,973 (100%)
Actually paid
$7,983,510 (56%)
Timeline
Mar 2, 2021Oct 31, 2024 · ended 637 days ago

Why this status?

  • Fully committed but $6,288,463 ordered is not yet paid — is the work being delivered?
  • Spending is behind schedule (100% of time elapsed, 56% paid).
  • High-dollar contract ($14,271,973) — worth periodic review.

These are transparent signals, not judgments. A large unspent balance may be a legitimate multi-year ceiling or indefinite-delivery contract.

Payments on this contract

No checkbook payments are booked directly against this contract number yet. This can happen when the work is paid through delivery orders under a master agreement (not directly linked here), or when payments simply haven’t started.

Linked via the contract number appearing as a payment’s source document (rf_doc_id = SA210000013) in the Austin checkbook. See all payments to this vendor →

Accountability

Administered by
Capital Contracting Office
Delivered by (1 firm)
SPAWGLASS CONTRACTORS INC

We couldn’t automatically match this contract to a City Council vote (the voting-record dataset starts in 2023, and older or consent-agenda items may not match by name). Most contracts are approved collectively on the Council consent agenda — so accountability runs through the managing department above and the Council vote on the award date, not an individual sponsor.

Documents & oversight

Contract type
Master agreement — a spending ceiling drawn down through individual delivery orders over time.

Assessing delivery vs. commitment: Austin doesn’t publish structured project milestones, so we can’t auto-verify that the work matches the contract. What we can do is show what the money was invoiced for (above) and link the approved scope — then, where it matters, dispatch a Spotter to confirm the work on the ground. Contracts whose purpose is well-documented vs. vague is exactly the signal that tells us where to look first.