Contracts explorer · Austin

Active City of Austin contracts · snapshot 2026-07-28 · 341 contracts · source dataset 84ih-p28j
These are public contract records. The colored status flags are transparent “worth a closer look” signals — not accusations. A large unspent balance is often a legitimate multi-year ceiling or an indefinite-delivery contract. This view shows money out to contractors; it is not a complete cash ledger and does not include revenue.
341
Active contracts
$2.4B
Authorized (ceilings)
$1.4B
Paid to date
52%
Funding source traced
by $ paid · 95 contracts
Why isn't every contract traced to one funding source?

A contract’s funding source is traced from the real checkbook funds its payments drew on — not guessed from its title. When one source is at least 60% of the dollars, we label it; otherwise it stays “Mixed / untraced” rather than mislabel a multi-fund master agreement.

Most checks reference a delivery order, which points at a downstream order rather than back to its master agreement — a known City-data linkage gap. So a payment can be clearly bucketed on the Recent big checks view (every check names its own fund) yet its parent contract here reads “Mixed.” That payment-first view classifies a higher share of dollars for exactly this reason.

Filter by funding source

Enterprise (fee-supported)

Self-supporting services paid by user fees — water, energy, airport, trash.

Approx scale~$3.9B · FY26 · 8 enterprise depts (Energy, Water, Aviation…)
Funded byUser fees & rates + revenue bonds (not your property tax)
Accountable toRatepayers/users + utility & airport oversight

Examples: Austin Water, Austin Energy, Airport (ABIA), Resource Recovery, Watershed/Drainage

Closer lookMonitorNominal
67 contracts · $595.7M paid · $668.1M authorized
SOUTH AUSTIN REGIONAL WWTP TRAINS A & B IMPROVEMENTS
Needs a closer look
MWH CONSTRUCTORS INCConstructionEnterpriseActiveContract and Land Management Department#22110700063
Authorized
$116,000,852
Ordered
$116,000,852
Actually paid
$63,793,269
55% of authorized paid
Kicked off Mar 2023 · last paid Jul 2026
  • Fully committed but $52,207,583 ordered is not yet paid — is the work being delivered?
  • High-dollar contract ($116,000,852) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
WILD HORSE RANCH WWTP EXPANSION
Needs a closer look
MATOUS CONSTRUCTION LTDConstructionEnterpriseActiveContract and Land Management Department#22120200114
Authorized
$69,588,255
Ordered
$69,588,255
Actually paid
$60,988,496
88% of authorized paid
Kicked off Apr 2023 · last paid Jul 2026
  • Fully committed but $8,599,759 ordered is not yet paid — is the work being delivered?
  • High-dollar contract ($69,588,255) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
ULLRICH WTP PROCESS DRAIN & SUPPORT SYSTEMS IMPROVEMENTS
Needs a closer look
PGC GENERAL CONTRACTORS, LLCConstructionEnterpriseActiveContract and Land Management Department#22061300635
Authorized
$14,225,871
Ordered
$14,225,871
Actually paid
$12,373,604
87% of authorized paid
Kicked off Oct 2022 · last paid Jul 2026
  • Fully committed but $1,852,267 ordered is not yet paid — is the work being delivered?
  • High-dollar contract ($14,225,871) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
OLTORF STREET RECLAIMED WATER MAIN PHASE 2
Needs a closer look
CASH CONSTRUCTION CO INCConstructionEnterpriseStalledContract and Land Management Department#23102400031
Authorized
$10,401,106
Ordered
$10,401,106
Actually paid
$8,902,847
86% of authorized paid
Kicked off Jul 2024 · last paid Jan 2026
  • Fully committed but $1,498,259 ordered is not yet paid — is the work being delivered?
  • High-dollar contract ($10,401,106) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
WALNUT CREEK WWTP GAS SCRUBBER SYSTEMS RENEWAL
Needs a closer look
MATOUS CONSTRUCTION II, LTDConstructionEnterpriseCompleteContract and Land Management Department#22121400131
Authorized
$6,565,953
Ordered
$6,565,953
Actually paid
$7,011,929
107% of authorized paid
Kicked off Mar 2023 · last paid Jun 2025
  • Payments ($7,011,929) exceed the authorized ceiling ($6,565,953) — worth a closer look.
  • No expiration date on record — timeline signals can't be computed.
BARTON HILLS WATER & WASTEWATER PIPELINE RENEWA
Needs a closer look
JKB CONSTRUCTION COMPANY, LLCConstructionEnterpriseCompleteContract and Land Management Department#22122700147
Authorized
$4,849,895
Ordered
$4,849,895
Actually paid
$5,182,364
107% of authorized paid
Kicked off May 2023 · last paid May 2025
  • Payments ($5,182,364) exceed the authorized ceiling ($4,849,895) — worth a closer look.
  • No expiration date on record — timeline signals can't be computed.
E. ALLANDALE WHITE ROCK NEIGHBRHD W&WW SYSTEM RENEWAL
Needs a closer look
VACA UNDERGROUND UTILITIES INCConstructionEnterpriseStalledContract and Land Management Department#20111700084
Authorized
$3,468,020
Ordered
$3,468,020
Actually paid
$591,521
17% of authorized paid
Kicked off Jan 2022 · last paid Sep 2024
  • Fully committed but $2,876,499 ordered is not yet paid — is the work being delivered?
  • No expiration date on record — timeline signals can't be computed.
HARMOND AVENUE AREA WATER AND WASTEWATER SYSTEM RENEWAL
Needs a closer look
SANTA CLARA CONSTRUCTION LTDConstructionEnterpriseCompleteContract and Land Management Department#20081701011
Authorized
$3,153,642
Ordered
$3,153,642
Actually paid
$3,469,050
110% of authorized paid
Kicked off May 2021 · last paid Nov 2025
  • Payments ($3,469,050) exceed the authorized ceiling ($3,153,642) — worth a closer look.
  • No expiration date on record — timeline signals can't be computed.
SAR ELEVATED TANK REHAB & IMPROVEMENTS - CIVIL WORK
Needs a closer look
PROTA, INC.ConstructionEnterpriseCompleteContract and Land Management Department#23092100763
Authorized
$2,136,347
Ordered
$2,136,347
Actually paid
$2,336,298
109% of authorized paid
Kicked off Feb 2024 · last paid Nov 2025
  • Payments ($2,336,298) exceed the authorized ceiling ($2,136,347) — worth a closer look.
  • No expiration date on record — timeline signals can't be computed.
WALNUT CREEK WWTP EFFLUENT SAMPLE PUMP MODIFICATIONS REBID
Needs a closer look
PGC GENERAL CONTRACTORS, LLCConstructionEnterpriseCompleteContract and Land Management Department#23092100764
Authorized
$1,767,194
Ordered
$1,767,194
Actually paid
$1,910,540
108% of authorized paid
Kicked off Jan 2024 · last paid Jul 2025
  • Payments ($1,910,540) exceed the authorized ceiling ($1,767,194) — worth a closer look.
  • No expiration date on record — timeline signals can't be computed.
DAVIS WATER TREATMENT PLANT TREATED WATER DISCHARGE SYSTEM
Monitor
MATOUS CONSTRUCTION LTDConstructionEnterpriseCompleteContract and Land Management Department#16040500516
Authorized
$45,676,261
Ordered
$45,676,261
Actually paid
$44,564,216
98% of authorized paid
Kicked off Sep 2016 · last paid Jan 2026
  • High-dollar contract ($45,676,261) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
NORTH AUSTIN RESERVOIR AND PUMP STATION IMPROVEMENTS
Monitor
MGC CONTRACTORS, INC.ConstructionEnterpriseCompleteContract and Land Management Department#20042000587
Authorized
$42,455,694
Ordered
$42,455,694
Actually paid
$42,324,750
100% of authorized paid
Kicked off Jul 2020 · last paid Dec 2025
  • High-dollar contract ($42,455,694) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
SOUTH AUSTIN REGIONAL WWTP ELECTRICAL SUBSTATION NO.1 REPLAC
Monitor
T MORALES COMPANY ELECTRIC & CONTROLS LTDNon-Professional ServicesEnterpriseActiveContract and Land Management Department#20042700606
Authorized
$31,188,997
Ordered
$31,188,997
Actually paid
$30,049,836
96% of authorized paid
Kicked off Sep 2020 · last paid Apr 2026
  • High-dollar contract ($31,188,997) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
WALNUT CREEK WWTP TERTIARY FILTER REHABILITATION
Monitor
PLW WATERWORKS, LLCConstructionEnterpriseCompleteContract and Land Management Department#17013000244
Authorized
$27,867,300
Ordered
$27,867,300
Actually paid
$27,867,300
100% of authorized paid
Kicked off May 2017 · last paid Dec 2023
  • High-dollar contract ($27,867,300) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
DAVIS WTP POWER DISTRIBUTION UPGRADE
Monitor
T MORALES COMPANY ELECTRIC & CONTROLS LTDConstructionEnterpriseCompleteContract and Land Management Department#16080400825
Authorized
$26,314,647
Ordered
$26,314,647
Actually paid
$25,999,150
99% of authorized paid
Kicked off Jan 2017 · last paid Jan 2026
  • High-dollar contract ($26,314,647) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
WALNUT CREEK WWTP SECONDARY PROCESS IMPROVEMENTS
Monitor
PLW WATERWORKS, LLCConstructionEnterpriseCompleteContract and Land Management Department#19092400894
Authorized
$24,879,795
Ordered
$24,879,795
Actually paid
$24,833,845
100% of authorized paid
Kicked off Mar 2020 · last paid Sep 2024
  • High-dollar contract ($24,879,795) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
HORNSBY BEND TRANSFER PUMP STATION AND IRRIGATION SYSTEM IMP
Monitor
PGC GENERAL CONTRACTORS, LLCConstructionEnterpriseCompleteContract and Land Management Department#20121600156
Authorized
$16,407,847
Ordered
$16,407,847
Actually paid
$16,226,149
99% of authorized paid
Kicked off May 2021 · last paid Oct 2025
  • High-dollar contract ($16,407,847) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
ULLRICH WATER TREATMENT PLANT LIME FEED LOOP
Monitor
MATOUS CONSTRUCTION II, LTDConstructionEnterpriseCompleteContract and Land Management Department#20021400358
Authorized
$12,678,818
Ordered
$12,678,818
Actually paid
$12,678,818
100% of authorized paid
Kicked off Jul 2020 · last paid May 2024
  • High-dollar contract ($12,678,818) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
RAINEY STREET GAS INSULATED SWITCHGEAR (GIS) SUBSTATION
Monitor
JAY-REESE CONTRACTORS INCConstructionEnterpriseCompleteContract and Land Management Department#21082400891
Authorized
$12,579,712
Ordered
$12,579,712
Actually paid
$12,579,712
100% of authorized paid
Kicked off Jan 2022 · last paid Apr 2024
  • High-dollar contract ($12,579,712) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
HORNSBY BEND BIOSOLIDS MANAGEMENT PLANT CENTRIFUGES
Monitor
MATOUS CONSTRUCTION II, LTDConstructionEnterpriseCompleteContract and Land Management Department#22020500342
Authorized
$11,152,006
Ordered
$11,152,006
Actually paid
$10,735,831
96% of authorized paid
Kicked off Jun 2022 · last paid Oct 2025
  • High-dollar contract ($11,152,006) — worth periodic review.
  • No expiration date on record — timeline signals can't be computed.
ZILKER WATER AND WASTEWATER PIPELINE RENEWAL
Nominal
M.A. SMITH CONTRACTING CO INCConstructionEnterpriseCompleteContract and Land Management Department#22110300053
Authorized
$9,123,963
Ordered
$9,123,963
Actually paid
$9,211,406
101% of authorized paid
Kicked off May 2023 · last paid Jun 2026
POLYBUTYLENE WATER SERVICES REPLACEMENT PROGRAM
Nominal
AUSTIN UNDERGROUND INCConstructionEnterpriseCompleteContract and Land Management Department#21121400227
Authorized
$9,105,680
Ordered
$9,105,680
Actually paid
$8,775,390
96% of authorized paid
Kicked off May 2022 · last paid Dec 2025
SOUTH TARRYTOWN WATER & WASTEWATER PIPELINE RENEWAL
Nominal
FACILITIES REHABILITATION INCConstructionEnterpriseActiveContract and Land Management Department#23080300599
Authorized
$9,072,300
Ordered
$9,072,300
Actually paid
$8,208,814
90% of authorized paid
Kicked off Dec 2023 · last paid Apr 2026
DAVIS & HANDCOX WTP POLYMER FEED SYS (2018 FLOOD RES. IMPMT)
Nominal
MATOUS CONSTRUCTION II, LTDConstructionEnterpriseCompleteContract and Land Management Department#22030700402
Authorized
$8,438,658
Ordered
$8,438,658
Actually paid
$8,250,956
98% of authorized paid
Kicked off Jul 2022 · last paid Jan 2026
ONION CREEK RECLAIMED WATER MAIN PHASE 1
Nominal
AUSTIN UNDERGROUND INCConstructionEnterpriseCompleteContract and Land Management Department#22082600851
Authorized
$8,252,332
Ordered
$8,252,332
Actually paid
$7,763,840
94% of authorized paid
Kicked off Dec 2022 · last paid Jan 2026
HYDE PARK WATER AND WASTEWATER PIPELINE RENEWAL
Nominal
SANTA CLARA CONSTRUCTION LTDConstructionEnterpriseCompleteContract and Land Management Department#21121400224
Authorized
$8,149,752
Ordered
$8,149,752
Actually paid
$7,801,001
96% of authorized paid
Kicked off Sep 2022 · last paid May 2025
SPRINGDALE AND 290 WATER LINE IMPROVEMENTS
Nominal
AUSTIN UNDERGROUND INCConstructionEnterpriseCompleteContract and Land Management Department#21092401032
Authorized
$7,064,341
Ordered
$7,064,341
Actually paid
$6,855,136
97% of authorized paid
Kicked off Feb 2022 · last paid Sep 2025
DAVIS WATER TREATMENT PLANT POWER DISTRIBUTION UPGRADE
Nominal
HARUTUNIAN ENGINEERING INCProfessional ServicesEnterpriseCompleteContract and Land Management Department#09051901445
Authorized
$6,994,382
Ordered
$6,994,382
Actually paid
$6,546,151
94% of authorized paid
Kicked off Jan 2010 · last paid Sep 2025
OLTORF STREET RECLAIMED WATER MAIN PHASE 1
Nominal
CASH CONSTRUCTION CO INCConstructionEnterpriseCompleteContract and Land Management Department#23030300260
Authorized
$6,639,466
Ordered
$6,639,466
Actually paid
$6,768,454
102% of authorized paid
Kicked off Jul 2023 · last paid Sep 2025
HIGHLAND PARK WATER AND WASTEWATER IMPROVEMENTS - PHASE 2
Nominal
SANTA CLARA CONSTRUCTION LTDConstructionEnterpriseCompleteContract and Land Management Department#21020400293
Authorized
$6,506,098
Ordered
$6,506,098
Actually paid
$6,402,276
98% of authorized paid
Kicked off Sep 2021 · last paid Jun 2025
ROCK HARBOUR LIFT STATION IMPROVEMENTS
Nominal
EXCEL CONSTRUCTION SERVICES, L L CConstructionEnterpriseCompleteContract and Land Management Department#22071800725
Authorized
$6,304,378
Ordered
$6,304,378
Actually paid
$6,542,210
104% of authorized paid
Kicked off Dec 2022 · last paid Jun 2025
SAR WWTP SLUDGE TRANSFER & RECLAIMED WATER LINE PROJECT
Nominal
AUSTIN UNDERGROUND INCConstructionEnterpriseCompleteContract and Land Management Department#21111800129
Authorized
$5,616,562
Ordered
$5,616,562
Actually paid
$5,616,562
100% of authorized paid
Kicked off May 2022 · last paid Jul 2024
SW ALLANDALE NEIGHBORHOOD WWW SYSTEM REHABILITATION
Nominal
CEDAR HILLS CONSTRUCTION LLCConstructionEnterpriseCompleteContract and Land Management Department#22040600497
Authorized
$5,531,518
Ordered
$5,531,518
Actually paid
$5,694,715
103% of authorized paid
Kicked off May 2022 · last paid May 2024
MORROW AND GAULT WATER & WASTEWATER PIPELINE RENEWAL
Nominal
SANTA CLARA CONSTRUCTION LTDConstructionEnterpriseCompleteContract and Land Management Department#20112000098
Authorized
$5,483,937
Ordered
$5,483,937
Actually paid
$5,377,015
98% of authorized paid
Kicked off Aug 2021 · last paid Mar 2025
DAVIS LANE # 1 RESERVOIR IMPROVEMENTS
Nominal
BLASTCO TEXAS INCConstructionEnterpriseCompleteContract and Land Management Department#19110100074
Authorized
$5,095,367
Ordered
$5,095,367
Actually paid
$5,068,386
99% of authorized paid
Kicked off Mar 2020 · last paid Aug 2024
WEST ALLANDALE AND TRAILRIDGE DRIVE UTILITY LINE RENEWAL
Nominal
SANTA CLARA CONSTRUCTION LTDConstructionEnterpriseCompleteContract and Land Management Department#19071800626
Authorized
$4,935,371
Ordered
$4,935,371
Actually paid
$5,071,722
103% of authorized paid
Kicked off Nov 2019 · last paid May 2025
NORTH TARRYTOWN WWW PIPELINE RENEWAL
Nominal
M.A. SMITH CONTRACTING CO INCConstructionEnterpriseCompleteContract and Land Management Department#21052000586
Authorized
$4,811,361
Ordered
$4,811,361
Actually paid
$4,816,159
100% of authorized paid
Kicked off Dec 2021 · last paid Mar 2025
VARGAS NEIGHBORHOOD WATER AND WASTEWATER PIPELINE RENEWAL
Nominal
SANTA CLARA CONSTRUCTION LTDConstructionEnterpriseCompleteContract and Land Management Department#22062800675
Authorized
$4,634,323
Ordered
$4,634,323
Actually paid
$4,377,977
94% of authorized paid
Kicked off Dec 2022 · last paid Feb 2025
ZEBRA MUSSEL MITIGATION
Nominal
EXCEL CONSTRUCTION SERVICES, L L CProfessional ServicesEnterpriseCompleteContract and Land Management Department#22062900680
Authorized
$4,491,157
Ordered
$4,491,157
Actually paid
$4,558,060
101% of authorized paid
Kicked off May 2023 · last paid Feb 2026
WASTEWATER COLLECTION SYSTEM REPLACEMENT LINES- NORTH
Nominal
FACILITIES REHABILITATION INCConstructionEnterpriseCompleteContract and Land Management Department#20013100314
Authorized
$4,201,715
Ordered
$4,201,715
Actually paid
$4,163,610
99% of authorized paid
Kicked off Aug 2020 · last paid Mar 2023
BOGGY CREEK - MLK TOD STORMWATER CONVEYANCE IMP PHASE 1
Nominal
M.A. SMITH CONTRACTING CO INCConstructionEnterpriseCompleteContract and Land Management Department#20030900458
Authorized
$3,913,080
Ordered
$3,913,080
Actually paid
$3,906,673
100% of authorized paid
Kicked off May 2020 · last paid May 2024
TRUMAN HEIGHTS WATER AND WASTEWATER PIPELINE REHABILITATION
Nominal
FACILITIES REHABILITATION INCConstructionEnterpriseCompleteContract and Land Management Department#22072200743
Authorized
$3,645,828
Ordered
$3,645,828
Actually paid
$3,502,334
96% of authorized paid
Kicked off Jun 2023 · last paid Oct 2024
ASBESTOS CEMENT WATER PIPE AND WW LINE REPLACEMENT (NE)
Nominal
UNDERGROUND WATER SOLUTIONS CO.ConstructionEnterpriseCompleteContract and Land Management Department#20123100188
Authorized
$3,520,113
Ordered
$3,520,113
Actually paid
$3,571,517
101% of authorized paid
Kicked off May 2021 · last paid Mar 2025
AEDP BUILDING DEMOLITION
Nominal
STR CONSTRUCTORS, LLCConstructionEnterpriseCompleteContract and Land Management Department#23032300302
Authorized
$3,501,472
Ordered
$3,501,472
Actually paid
$3,604,126
103% of authorized paid
Kicked off Jul 2023 · last paid May 2024
SLAUGHTER LANE AND CAPITAL OF TEXAS RESERVOIR IMPROVEMENTS
Nominal
BLASTCO TEXAS INCNon-Professional ServicesEnterpriseCompleteContract and Land Management Department#20120100122
Authorized
$3,430,072
Ordered
$3,430,072
Actually paid
$3,469,361
101% of authorized paid
Kicked off Mar 2021 · last paid Jun 2024
BULL CREEK WASTEWATER PIPELINES RENEWAL
Nominal
FACILITIES REHABILITATION INCConstructionEnterpriseCompleteContract and Land Management Department#23101600017
Authorized
$3,288,275
Ordered
$3,288,275
Actually paid
$3,233,821
98% of authorized paid
Kicked off May 2024 · last paid Nov 2025
ROSEDALE NORTH WATER AND WASTEWATER PIPELINE RENEWAL PHASE 2
Nominal
UNDERGROUND WATER SOLUTIONS CO.ConstructionEnterpriseCompleteContract and Land Management Department#21061500672
Authorized
$3,233,057
Ordered
$3,233,057
Actually paid
$3,177,853
98% of authorized paid
Kicked off Sep 2021 · last paid Mar 2026
MEDICAL ARTS SQUARE WATER AND WASTEWATER SYSTEM RENEWAL
Nominal
PGC GENERAL CONTRACTORS, LLCConstructionEnterpriseCompleteContract and Land Management Department#22021800372
Authorized
$3,140,554
Ordered
$3,140,554
Actually paid
$2,985,060
95% of authorized paid
Kicked off Jun 2022 · last paid Apr 2024
WALLER CREEK - INLET FACILITY WET WELL MECHANICAL SCREENING
Nominal
MATOUS CONSTRUCTION II, LTDCommodities (Goods)EnterpriseCompleteContract and Land Management Department#23090100693
Authorized
$2,650,000
Ordered
$2,650,000
Actually paid
$2,686,273
101% of authorized paid
Kicked off Aug 2024 · last paid Mar 2026
FORT UPPER BASIN WATER AND WASTEWATER PIPELINE RENEWAL
Nominal
FACILITIES REHABILITATION INCConstructionEnterpriseCompleteContract and Land Management Department#21120700211
Authorized
$2,642,686
Ordered
$2,642,686
Actually paid
$2,507,027
95% of authorized paid
Kicked off Oct 2022 · last paid Oct 2024
HORNSBY BEND BIOSOLIDS MANAGEMENT PLANT ROADWAY IMPROVEMENTS
Nominal
JERDON ENTERPRISE, LPConstructionEnterpriseCompleteContract and Land Management Department#23061600495
Authorized
$2,362,877
Ordered
$2,362,877
Actually paid
$2,161,517
91% of authorized paid
Kicked off Nov 2023 · last paid Jul 2024
ACADEMY DRIVE WATER AND WASTEWATER PIPELINE RENEWAL
Nominal
FACILITIES REHABILITATION INCConstructionEnterpriseCompleteContract and Land Management Department#22051000565
Authorized
$2,360,123
Ordered
$2,360,123
Actually paid
$2,264,853
96% of authorized paid
Kicked off Feb 2023 · last paid Nov 2024
WATER DISTRIBUTION CONTROL SYSTEM& LIFT STATION TELEMETRY
Nominal
CH2M HILL INCSole and Single SourceEnterpriseCompleteContract and Land Management Department#09060501513
Authorized
$2,100,903
Ordered
$2,100,903
Actually paid
$2,098,616
100% of authorized paid
Kicked off Nov 2009 · last paid Dec 2025
WEST 9TH AND 12TH STREETS WATER AND WASTEWATER RENEWAL
Nominal
UNDERGROUND WATER SOLUTIONS CO.ConstructionEnterpriseCompleteContract and Land Management Department#21061600676
Authorized
$2,040,960
Ordered
$2,040,960
Actually paid
$2,140,626
105% of authorized paid
Kicked off Sep 2021 · last paid Jul 2024
AUSTIN ENERGY-SCC ROOF REPLACEMENT
Nominal
PORT ENTERPRISES LTDConstructionEnterpriseCompleteContract and Land Management Department#23110700055
Authorized
$1,945,000
Ordered
$1,945,000
Actually paid
$1,923,367
99% of authorized paid
Kicked off Feb 2024 · last paid Nov 2024
CISTERN SUBSTATION CUT-IN AND CKT 3121/3136 OPGW ADDITION
Nominal
KIEWIT INFRASTRUCTURE SOUTH CO.ConstructionEnterpriseCompleteContract and Land Management Department#21080900827
Authorized
$1,531,694
Ordered
$1,531,694
Actually paid
$1,531,694
100% of authorized paid
Kicked off Dec 2021 · last paid Mar 2024
BRYKER ROAD WATER AND WASTEWATER PIPELINE RENEWAL
Nominal
SANTA CLARA CONSTRUCTION LTDConstructionEnterpriseCompleteContract and Land Management Department#21050500544
Authorized
$1,498,159
Ordered
$1,498,159
Actually paid
$1,409,409
94% of authorized paid
Kicked off Sep 2021 · last paid Feb 2025
STARLINE DRIVE AND LAWNDALE DRIVE PRESSURE ZONE CONVERSION
Nominal
FACILITIES REHABILITATION INCConstructionEnterpriseCompleteContract and Land Management Department#23092200767
Authorized
$1,450,995
Ordered
$1,450,995
Actually paid
$1,431,484
99% of authorized paid
Kicked off Mar 2024 · last paid Mar 2026
GOVALLE SITE DOMESTIC WASTEWATER SERVICE IMPROVEMENTS
Nominal
UDELHOVEN, INC.Commodities (Goods)EnterpriseCompleteContract and Land Management Department#22090800881
Authorized
$1,199,428
Ordered
$1,199,428
Actually paid
$1,211,351
101% of authorized paid
Kicked off May 2024 · last paid Mar 2026
HANDCOX WATER TREATMENT PLANT PROCESS BLDG HVAC IMPR PROJECT
Nominal
PGC GENERAL CONTRACTORS, LLCConstructionEnterpriseCompleteContract and Land Management Department#21102200055
Authorized
$1,038,603
Ordered
$1,038,603
Actually paid
$1,035,911
100% of authorized paid
Kicked off Mar 2022 · last paid Apr 2025
BEVERLY ROAD WATER AND WASTEWATER PIPELINE RENEWAL
Nominal
UNDERGROUND WATER SOLUTIONS CO.ConstructionEnterpriseCompleteContract and Land Management Department#21090800955
Authorized
$924,062
Ordered
$924,062
Actually paid
$924,062
100% of authorized paid
Kicked off Mar 2022 · last paid Jan 2024
DAVIS WTP FILTER MEDIA TANK IMPROVEMENTS
Nominal
MATOUS CONSTRUCTION II, LTDConstructionEnterpriseCompleteContract and Land Management Department#22042500525
Authorized
$875,916
Ordered
$875,916
Actually paid
$802,198
92% of authorized paid
Kicked off Dec 2022 · last paid Mar 2024
MOTHERAL DRIVE SITE IMPROVEMENTS
Nominal
MAJESTIC SERVICES INCConstructionEnterpriseCompleteContract and Land Management Department#23070700550
Authorized
$823,447
Ordered
$823,447
Actually paid
$839,164
102% of authorized paid
Kicked off Nov 2023 · last paid Sep 2024
OFFICE TRAILERS
Nominal
TSG INDUSTRIES LLCCommodities (Goods)EnterpriseCompleteCentral Purchasing Office Receptionist#22091500897
Authorized
$492,880
Ordered
$492,880
Actually paid
$443,592
90% of authorized paid
Kicked off Jan 2023 · last paid Sep 2023
ONION CREEK ODOR CONTROL FACILITY STREAM BANK STABILIZATION
Nominal
FORSYTHE BROTHERS INFRASTRUCTURE, LLC.Commodities (Goods)EnterpriseCompleteContract and Land Management Department#23020600204
Authorized
$390,000
Ordered
$390,000
Actually paid
$388,828
100% of authorized paid
Kicked off Feb 2024 · last paid Sep 2024
AFS LEAD REMEDIATION
Nominal
1 PRIORITY ENVIRONMENTAL SERVICES, LLCNon-Professional ServicesEnterpriseStalledContract and Land Management Department#23031300282
Authorized
$169,659
Ordered
$169,659
Actually paid
$80,222
47% of authorized paid
Kicked off Aug 2023 · last paid Aug 2023
GAS CHROMATOGRAPH-MASS SPECTROPHOTOMETER
Nominal
SHIMADZU SCIENTIFIC INSTRUMENTS INCCommodities (Goods)EnterpriseCompleteCentral Purchasing Office Receptionist#23080400604
Authorized
$130,000
Ordered
$130,000
Actually paid
$128,151
99% of authorized paid
Kicked off Aug 2024 · last paid Aug 2024

Scope note: this tracks money out (spending), not revenue. General-Fund spend is only partly visible here — we see it where it flows through vendors (e.g. Parks maintenance), not payroll. The fund types follow the City of Austin’s governmental fund accounting; scale figures are approximate, as of FY2026.